Residential Renewable Energy Generation in Mexico

Derived from various provisions established in the National Development Plan 2007-2012, in the Law for the Use of Renewable Energies and the Financing of the Energy Transition, its Regulations, as well as in the Special Climate Change Program 2008-2012; now you can install in your home or business, your own renewable energy source or cogeneration system on a small or medium scale and make an interconnection contract with CFE.

By doing so, in addition to saving on your expenditure on energy consumption, you will contribute to the use of clean technologies for the generation of electricity, in the use of renewable energy sources and therefore, in the conservation of the environment.

The requirements to make a small-scale interconnection contract with CFE are that you have a normal low voltage supply contract, that the facilities comply with the Official Mexican Standards and with the CFE specifications, and that the power of your source is not greater than 10 kW if you installed it in your home or 30 kW if you installed it in your business.

To make a medium-scale interconnection contract, the requirements are that you have a normal medium voltage supply contract, that the facilities comply with the Official Mexican Standards and with the CFE specifications, and that the power of your source is not greater than 500 kW.

- Publicidad -

The duration of the contract is indefinite and can be terminated whenever you wish, notifying CFE 30 days before.

Currently, the CFE records your electricity consumption with meters that only integrate the energy you receive from our network. When establishing an interconnection contract, CFE will change the meter, installing one that will allow you to record both the electrical energy that enters your service, and the electrical energy that leaves.

From that moment, CFE will invoice you in your normal supply contract, the difference between both records, and three cases may occur:

a) If the difference is greater than zero, it means that you consumed more energy than you delivered, so you will be billed for that difference.

b) If the difference is equal to zero, it means that you consumed the same amount of energy as the one you delivered, so you will be billed the minimum established in the rate at which you have your normal supply contract.

c) If the difference is less than zero, then it means that you delivered more energy than you consumed, so we will proceed to:

a. bill you the minimum established in the rate at which you have your normal supply contract and
b. CFE will virtually save the energy that was left in your favor, to automatically return it to you in the following billings in which differences greater than zero are presented.

- Publicidad -

The steps to follow to perform the interconnection contract are the following:

1. Go to the nearest CFE commercial agency, using the following format:

sustainability/renewable energy/Documents/application%20for%20la%20connection.pdf">Format to request interconnection with CFE

The person who must carry out the procedure must be the holder of the normal supply contract, if he is a natural person, or the legal representative, if he is a legal person. In both cases, official identification is required. In the case of a legal entity, the representative must also present the documentation that proves the constitution of the company and the empowerment of the same towards the person who carries out the procedure.

2. You will receive a request number, with which you can follow up on it.

3. Cfe technical area personnel will come to your home to check that the energy source or cogeneration system meets the corresponding technical requirements. It will inform you of the results of the review, and where appropriate, of the works that need to be built or modified to carry out the interconnection, which will be borne by the applicant.

- Publicidad -

4. Once it has been technically approved, the person carrying out the procedure will go again to the nearest CFE commercial agency to sign their interconnection contract and pay the amount corresponding to the difference in costs of the meters.

5. CFE technical staff will come to your home to change the meter.

6. From that moment on, you will already have an interconnection contract with CFE.

Authors: Val

See Original.

Free Subscription
SUBSCRIBE TO OUR NEWSLETTER
DO YOU NEED A SERVICE OR PRODUCT QUOTE?
LASTEST INTERVIEWS

Entrevista a Jaime Maldonado, Presidente de Air-Con Inc

En entrevista con ACR Latinoamérica, Jaime Maldonado, Presidente de Air-Con Inc, destacó los proyectos que tiene la compañía para este año 2024, sobre todo con la transición de los nuevos refrigerantes. Además, Air-Con estará como expositor en Refriaméricas Miami, y Jaime nos habló sobre sus expectativas con el evento y lo que darán a conocer para todos los visitantes.

Webinar: Armstrong y Energía de Distrito

Por: Rafael Behar, Gerente de Apoyo de Aplicación, Armstrong Fluid Technology Los sistemas de energía de distrito se caracterizan por una o más plantas centrales que producen agua caliente, vapor y/o agua fría, que luego fluye a través de una red de tuberías aisladas para proporcionar agua caliente, calefacción y/o aire acondicionado a los edificios cercanos. Los sistemas de energía de distrito sirven a una variedad de mercados de uso final, incluidos los centros de las ciudades (distritos comerciales centrales), campus universitarios, hospitales e instalaciones de atención médica, aeropuertos, bases militares y complejos industriales. Al combinar cargas para múltiples edificios, los sistemas de energía urbana crean economías de escala que ayudan a reducir los costos de energía y permiten el uso de tecnologías de alta eficiencia. En este seminario web vamos a introducir a Armstrong Fluid Tecnología y su dirección para la energía urbana con enfoques en plantas de calefacción. https://www.acrlatinoamerica.com/20...

Webinar: Mejores Practicas para la Optimización de Sistemas

Importancia de la correcta automatización de plantas de agua helada con el objetivo de pasar al siguiente nivel, que es la optimización de los sistemas para obtener una mayor eficiencia energética y ahorro del costo operativo y de mantenimiento. Por: Camilo Olvera Rodríguez, Gerente de Ventas - México, ARMSTRONG FLUID TECHNOLOGY https://www.acrlatinoamerica.com/20...

Webinar: Enfriando el futuro: Las nuevas tendencias en refrigerantes para supermercados y almacenes

https://www.acrlatinoamerica.com/20... Únete a nosotros en este emocionante Webinar sobre las últimas tendencias en refrigerantes para supermercados y almacenes. Descubre cómo mantener tus productos frescos de manera eficiente, mientras contribuyes a la sostenibilidad y cuidado del medio ambiente. En esta sesión, exploraremos las innovaciones más recientes en refrigerantes ambientalmente preferibles, incluyendo tecnologías avanzadas de enfriamiento. Aprenderás sobre las ventajas de adoptar estas nuevas soluciones, no solo en términos de eficiencia energética, sino también en la reducción de emisiones y el cumplimiento de regulaciones ambientales. Por: Guillermo Brandenstein, Sr Account Manager - Honeywell

Webinar: ¿Es adecuada la forma de vender en las empresas HVAC/R?

En esta presentación se tratarán puntos neurálgicos sobre cómo lograr vender sin necesidad de licitar, teniendo muy presente que el cliente no nos compre porque somos los más baratos sino porque somos su mejor opción. Por: Ing. Rolando Torrado, CEO - Rolando Torrado https://www.acrlatinoamerica.com/20...
Load more...
SITE SPONSORS










LASTEST NEWSLETTER
Ultimo Info-Boletin